Orange Group Georgia, legal guide “Construction and Commissioning. Batumi 2026”
Published 16 November 2026, facts checked as of 10 November 2026
In Georgia, a building permit and the commissioning of a building are two independent legal decisions. The permit allows the construction works it covers. It does not give the right to use the finished building.
Commissioning is a public-law decision confirming that construction is complete and the building meets the applicable requirements. It is not the same as an apartment handover act, ownership registration, final payment under the contract or the handing over of keys.
As a general rule, no. Article 139¹ of Georgia’s Construction Code expressly prohibits the operation of a building before the commissioning act. Ownership rights and residents living there do not make the building lawfully commissioned.
A typical situation: the developer says “people live here, there is power and water, so everything is legal”. None of these facts proves that a commissioning act exists.
| Sign | What it confirms | What it does not confirm |
|---|---|---|
| Ownership is registered | A record of the property right | Acceptance of the building and lawful occupancy |
| Keys handed over | Actual possession | Compliance with technical and fire safety rules |
| People live there | Actual use of the premises | That a commissioning act exists |
| Power and water connected | The fact of connection | That the connection and occupancy are lawful |
| Lifts are working | Technical capability | Official testing and the commissioning act |
| All payments made | The financial part of the contract | Completion of the administrative process |
A full comparison of commissioned and non-commissioned buildings — living, utilities, resale and mortgages — is in the complete guide.
Get the guide on TelegramFor permits issued before 03.06.2019, a transitional regime applies: commissioning follows the rules in force when the permit was issued. So for an older building you first need to establish the permit date and the applicable transitional rules, and only then assess the documents.
Government Resolution No. 62 of 16.02.2026 set separate deadlines for Tbilisi and other municipalities. In Batumi, the commissioning decision is made within:
Deadlines run from the proper submission of a complete set of documents.
The applicant chooses a two-stage or three-stage procedure. Two stages: development conditions — 10 working days, permit together with the design — 20. Three stages: conditions — 10, architecture — 17, permit — 5. That is 30 or 32 working days of nominal review.
This is the review time of the authority, not of the development project. Geology, design, expert reviews, demolition and corrections are not included.
Supplying a complex through a construction connection or a single meter cannot automatically be treated as proper household supply for each apartment.
Typical reasons that follow from the law and the permit documentation:
Article 141⁷ of the Code creates an exceptional regime for recognising certain buildings in Batumi with deviations from the design as fit for use. It applies only to the buildings and deadlines expressly set in the law and requires confirmation of structural and seismic safety. The application window under this regime was limited, and no general extension was found as of November 2026.
Article 141⁶ is a separate mechanism for reconstructing and replacing dilapidated apartment buildings in Batumi. It is not a way to legalise an unauthorised high-rise. In the current version, the programme runs until 01.01.2027.
A 16-stage project life cycle, demolition, land transactions, landscaping and the Supreme Court of Georgia ruling of 05.02.2026.
Download free on TelegramAs a general rule, no. Article 139¹ of Georgia’s Construction Code prohibits the operation of a building before the commissioning act. People actually living there does not make the building lawfully commissioned.
The decision is made within 15 working days for Class II buildings and Class III buildings up to 1,500 m², 20 working days for Class III buildings over 1,500 m² and 30 working days for Class IV. The deadline runs from the proper submission of a complete set of documents.
The law contains no general prohibition: ownership of an apartment can be registered before commissioning. But the right to own and the right to lawfully use a building are different questions. Banks and insurers may treat the lack of commissioning as a significant risk.
Article 139¹ prohibits supplying electricity and natural gas to a building that has not been commissioned. The exception is supply for construction works while the permit is valid. Water and sewerage are governed by separate rules.
It is an exceptional regime for recognising certain buildings in Batumi with deviations from the design as fit for use. It applies only to the buildings and deadlines expressly set in the law and is not an automatic amnesty for all unfinished buildings.
This material is based on Georgia’s Construction Code, government resolutions, acts of the Batumi City Council (Sakrebulo), GNERC rules and published case law, checked as of 10.11.2026. It is a research guide, not a legal opinion on a specific property. A decision about a specific building requires a lawyer to review the documents.