Source: Orange Group Georgia

Can you live in a building that has not been commissioned? What buyers in Batumi should check

Orange Group Georgia, legal guide “Construction and Commissioning. Batumi 2026”
Published 16 November 2026, facts checked as of 10 November 2026

Key points

  • A building permit and commissioning (acceptance into operation) are two separate decisions. The first allows construction, the second allows the finished building to be used.
  • As a general rule, a building may not be operated before commissioning — Article 139¹ of Georgia’s Construction Code.
  • Registered ownership, keys, electricity, water and working lifts do not prove that the building has been commissioned.
  • In Batumi, the commissioning decision is made within 15, 20 or 30 working days, depending on the building class.
  • The “Batumi amnesty” under Article 141⁷ is an exceptional regime for specific buildings, not a legalisation of every unfinished project.

A permit and commissioning are different decisions

In Georgia, a building permit and the commissioning of a building are two independent legal decisions. The permit allows the construction works it covers. It does not give the right to use the finished building.

Commissioning is a public-law decision confirming that construction is complete and the building meets the applicable requirements. It is not the same as an apartment handover act, ownership registration, final payment under the contract or the handing over of keys.

Can you live in a building without commissioning?

As a general rule, no. Article 139¹ of Georgia’s Construction Code expressly prohibits the operation of a building before the commissioning act. Ownership rights and residents living there do not make the building lawfully commissioned.

At the same time, the lack of commissioning does not always make the purchase of an apartment invalid. The right to own and the right to lawfully use a building are different questions, and mixing them up is a common legal mistake.

What does not prove commissioning

A typical situation: the developer says “people live here, there is power and water, so everything is legal”. None of these facts proves that a commissioning act exists.

Signs that are often mistaken for commissioning
SignWhat it confirmsWhat it does not confirm
Ownership is registeredA record of the property rightAcceptance of the building and lawful occupancy
Keys handed overActual possessionCompliance with technical and fire safety rules
People live thereActual use of the premisesThat a commissioning act exists
Power and water connectedThe fact of connectionThat the connection and occupancy are lawful
Lifts are workingTechnical capabilityOfficial testing and the commissioning act
All payments madeThe financial part of the contractCompletion of the administrative process
Legal guide · 44 pages · in Russian

A full comparison of commissioned and non-commissioned buildings — living, utilities, resale and mortgages — is in the complete guide.

Get the guide on Telegram

The permit date matters more than the purchase date

For permits issued before 03.06.2019, a transitional regime applies: commissioning follows the rules in force when the permit was issued. So for an older building you first need to establish the permit date and the applicable transitional rules, and only then assess the documents.

Commissioning deadlines in Batumi

Government Resolution No. 62 of 16.02.2026 set separate deadlines for Tbilisi and other municipalities. In Batumi, the commissioning decision is made within:

15 daysClass IIworking days for the decision
15 daysClass III up to 1,500 m²working days for the decision
20 daysClass III over 1,500 m²working days for the decision
30 daysClass IVworking days for the decision

Deadlines run from the proper submission of a complete set of documents.

How long a building permit takes

The applicant chooses a two-stage or three-stage procedure. Two stages: development conditions — 10 working days, permit together with the design — 20. Three stages: conditions — 10, architecture — 17, permit — 5. That is 30 or 32 working days of nominal review.

This is the review time of the authority, not of the development project. Geology, design, expert reviews, demolition and corrections are not included.

Electricity, gas, water and sewerage

  • Electricity and gas. Article 139¹ prohibits supplying them to a building that has not been commissioned. The exception is supply for construction works while the permit is valid.
  • Water. Not named in the direct prohibition, but not automatically allowed either: separate technical and subscriber rules apply.
  • Sewerage. A separate engineering regime: an available network, operator requirements and approved connection points.

Supplying a complex through a construction connection or a single meter cannot automatically be treated as proper household supply for each apartment.

Why buildings in Batumi remain uncommissioned

Typical reasons that follow from the law and the permit documentation:

  • architectural deviations: an extra floor, a changed footprint, area, façade or height;
  • exceeding the K1/K2/K3 coefficients, breaching setbacks, missing landscaping;
  • unfinished common areas: lobbies, parking, entrances, driveways;
  • utility networks and fire safety systems not ready;
  • missing stage acts, surveys, lift tests or expert reviews;
  • disputes over demolition of an old building and third-party rights;
  • expired permits, stopped works, financial problems of the developer.

The “Batumi amnesty” and renovation

Article 141⁷ of the Code creates an exceptional regime for recognising certain buildings in Batumi with deviations from the design as fit for use. It applies only to the buildings and deadlines expressly set in the law and requires confirmation of structural and seismic safety. The application window under this regime was limited, and no general extension was found as of November 2026.

Article 141⁶ is a separate mechanism for reconstructing and replacing dilapidated apartment buildings in Batumi. It is not a way to legalise an unauthorised high-rise. In the current version, the programme runs until 01.01.2027.

Also in the guide

A 16-stage project life cycle, demolition, land transactions, landscaping and the Supreme Court of Georgia ruling of 05.02.2026.

Download free on Telegram

Frequently asked questions

Can you live in a building that has not been commissioned in Georgia?

As a general rule, no. Article 139¹ of Georgia’s Construction Code prohibits the operation of a building before the commissioning act. People actually living there does not make the building lawfully commissioned.

How long does building commissioning take in Batumi?

The decision is made within 15 working days for Class II buildings and Class III buildings up to 1,500 m², 20 working days for Class III buildings over 1,500 m² and 30 working days for Class IV. The deadline runs from the proper submission of a complete set of documents.

Can you buy and register an apartment in a building without commissioning?

The law contains no general prohibition: ownership of an apartment can be registered before commissioning. But the right to own and the right to lawfully use a building are different questions. Banks and insurers may treat the lack of commissioning as a significant risk.

Is electricity and gas connected to a building that has not been commissioned?

Article 139¹ prohibits supplying electricity and natural gas to a building that has not been commissioned. The exception is supply for construction works while the permit is valid. Water and sewerage are governed by separate rules.

What is Article 141⁷ and who does it apply to?

It is an exceptional regime for recognising certain buildings in Batumi with deviations from the design as fit for use. It applies only to the buildings and deadlines expressly set in the law and is not an automatic amnesty for all unfinished buildings.

Disclaimer

This material is based on Georgia’s Construction Code, government resolutions, acts of the Batumi City Council (Sakrebulo), GNERC rules and published case law, checked as of 10.11.2026. It is a research guide, not a legal opinion on a specific property. A decision about a specific building requires a lawyer to review the documents.

CONTACTS
The most up-to-date information is available
on our social media
+995 706 706 428
131a Petre Bagrationi Street, Batumi